MuNa/ref/Muna Technical Bases for Stage 1.txt

1384 lines
41 KiB
Text
Raw Normal View History

2026-07-18 20:29:02 +01:00
Open Call for Architectural schematic design
proposals for the New Building of the National
Museum of Ecuador
Participation Rules
Stage 1
Presidency of the Republic of Ecuador
President
Daniel Noboa Azín
Vice president
María José Pinto González-Artigas
Ministry of Education, Sports and Culture
Minister
Gilda Alcívar García
Deputy Minister of Culture
Romina Muñoz Procel
Undersecretary of Social Memory
María Carla Freile Freile
National Museum of Ecuador
Chief executive officer
Carlos Montalvo Puente
College of Architects of Ecuador - Pichincha
President
Diego Ordóñez Holguín
Vice president
Daniela Loaiza Jiménez
International Advisor
Hernán Crespo Bermejo
OVERVIEW
Scope
The Government of Ecuador, through the Ministry of Education, Sports and Culture and with
the technical advice of the College of Architects of Ecuador (CAE-P), calls for the preparation of the architectural preliminary project for the new building of the National Museum
of Ecuador—an institution that safeguards more than 1.2 million cultural and heritage assets spanning 12,000 years of history and forming the most important collection in the country.
The objective is to consolidate the National Museum as a cultural platform of national significance
and a touristic reference for Quito, the first UNESCO World Heritage City, through a new building
that integrates exhibition rooms, conservation and research areas, educational spaces, public areas,
and a landscape plan that strengthens its relationship with the urban environment.
Location and area of the property
Av. Eloy Alfaro and Av. de la República, Iñaquito parish, Quito - Pichincha - Ecuador
13.004,65 m²
Minimum projected area for the new building
25,000 m²
Requirements and modality
National and international Open Call
The Open Call is aimed at national and international architects with multidisciplinary teams who
can demonstrate, through previous projects, the ability to undertake a project of this scale and
complexity, showing solvency in architectural conceptualization, urban integration, and the programmatic resolution of cultural facilities.
Stages
The Open Call will be carried out in two stages:
Stage 1: Open Call for the submission of credentials and portfolios.
Stage 2: Architectural Design Proposals (Schematic design), in which only the teams selected
in the previous stage—those that demonstrate the professional and technical solvency and
experience required for a project of this magnitude—will participate.
Recognition
Stage 1 does not include financial prizes; its objective is to select the teams with the necessary
solvency to advance to the next phase. In Stage 2, there will be only one winner, who will receive
USD 450,000 for the complete delivery of the preliminary project.
Stage 1 Submission Deadline
February 17, 2026 23:59 (UTC-5)
Applications must be submitted by email to: convocatoria@museonacional.gob.ec
Questions regarding the open call should be sent to: preguntas@museonacional.gob.ec
Website:
https://construccion.museonacional.gob.ec
I.
NATIONAL MUSEUM
OF ECUADOR
II.
LOCATION
III. PARTICIPATION
REQUIREMENTS - STAGE 1
IV. SCHEDULE AND DELIVERY
METHOD - STAGE 1
V.
SELECTION PROCESS
- STAGE 1
VI. ANNEXES
I. NATIONAL MUSEUM
OF ECUADOR
5
I. NATIONAL MUSEUM
OF ECUADOR
The National Museum of Ecuador was inaugurated in 1969 as the Guillermo Pérez Chiriboga
Archaeological Museum and Galleries of the
Central Bank of Ecuador, under the direction of
architect Hernán Crespo Toral.
Its first home was the Central Banks headquarters building, located across from Alameda Park,
where the museum quickly became one of the
countrys most significant cultural institutions.
From this location, it advanced the preservation,
research, and interpretation of Ecuadors archaeological, ethnographic, and artistic heritage,
assembling collections that represent diverse regions and cultural traditions of the nation.
Educational activities at the “Guillermo Pérez Chiriboga”
Archaeological Museum and Galleries
During the 1980s, following a period of notable
institutional growth and increasing international
visibility, a public tender was launched for the
construction of a purpose-built museum building
in Itchimbía Park. The process, however, was ultimately declared void.
In 1995, the museums exhibition spaces were
temporarily relocated to the newly constructed
Edificio de los Espejos of the Casa de la Cultura
Ecuatoriana, opening to the public on June 30
under the name National Museum of the Central Bank of Ecuador. The collections storage
areas were transferred to the Aranjuez Building
on Reina Victoria Street. Simultaneously, plans
were developed to install the National Museum
permanently within the Central Banks headquarters, with the aim of dedicating the entire building to cultural functions and relocating banking
services to what is now the North Platform. This
initiative, however, did not come to fruition.
Central Bank of Ecuador building that housed the museum
from 1969 to 1995
Current entrance to the National Museum of Ecuador,
Edificio de los Espejos, Casa de la Cultura Ecuatoriana
6
In 2007, the cultural functions of the Central Bank were transferred to the Ministry of Culture and
Heritage, which subsequently promoted several projects aimed at improving the museums facilities.
In 2015, the National Museum closed to undergo a comprehensive architectural and museographic
renewal, reopening in May 2018 within the same building. Today, the National Museum of Ecuador
is one of the most visited museums in the country; however, it continues to operate in a facility that
no longer meets its technical, spatial, operational, or institutional needs. Notably, the museum is
currently able to exhibit less than 1% of its collections due to limited gallery space, insufficient museographic infrastructure, and inadequate environmental controls for the safe display of artworks
and cultural objects.
The construction of a purpose-built facility for the National Museum of Ecuador represents an unprecedented milestone in the nations cultural policy and a decisive advance in the stewardship of its
cultural heritage. It offers a strategic opportunity to redefine the museums role in contemporary
society, strengthening its leadership in the research, conservation, and dissemination of Ecuadors
cultural patrimony and collective memory. This project will reinforce cultural identity and social belonging among Ecuadorians, establishing an institutional legacy for generations to come.
7
The National Collection
The National Collection brings together a wide
diversity of Ecuadors cultural and heritage
assets, ranging from archaeological objects and
colonial and republican works of art to historical
documentary collections and modern and contemporary artworks. It includes ceramics, textiles, documents, books, sculptures, paintings,
and audiovisual records, along with other artistic media and typologies that reflect the creative and material richness of the countrys diverse
peoples, cultures, and artists.
The National Museum safeguards and manages
an essential part of this collection, organized
into specialized collections reserves according to
their nature, period, and typology:
Archaeology Reserve:
62,103 from the cultures and societies that developed in what is now Ecuador, spanning early lithic
tools—such as obsidian projectile points—to Manteño stone seats and the emblematic Tolita Sun.
Colonial and Republican Reserve:
5,353 including colonial altarpieces; sculptures
by Bernardo de Legarda; and drawings, paintings,
and devotional works from the republican period,
notably pieces by Joaquín Pinto.
Modern and Contemporary Art Reserve:
2,538 works by key figures of Ecuadorian art,
including Luis A. Martínez, Araceli Gilbert, and
other leading exponents of twentieth- and twenty-first-century artistic production.
Human Sciences Library:
Approximately 210,000 bibliographic holdings—
books, journals, newspapers, maps, atlases, and
rare printed materials—many of them patrimonial and dating from 1480 to the present. The library integrates notable collections such as those of Jacinto Jijón y Caamaño and Isaac Barrera,
with strengths in the social sciences, arts, and
national history.
Historical Archive of the National Museum:
918,673 archival documents, including colonial
manuscripts through the early twentieth century, as well as photographic collections, musical
scores, sound and radio recordings, cartography, posters, and other documentary materials
essential for the study of Ecuadors historical
development.
8
II. LOCATION
II. LOCATION
The new building of the National Museum of Ecuador will be situated on a 13,004.65 m² site located
on the southwestern corner of Eloy Alfaro Avenue and Republic Avenue, in the city of Quito, Ecuador.
The plot forms part of the “La Pradera” Urban Action Unit, a strategic node for urban development
and the creation of high-quality public spacein the citys centralnorthern corridor. The area is envisioned as the anchor of a future pedestrian boulevard that will connect public facilities, green areas,
and recreational spaces, consolidating a high-quality urban environment.
The site lies diagonally across from La Carolina Park, one of the most emblematic and frequented
public spaces in Quito, attracting an average of 400,000 visitors per month. his exceptional location positions the project at the heart of one of the capitals main cultural and recreational districts,
offering a unique opportunity to integrate the museum seamlessly into the broader urban fabric and
enhance its visibility, accessibility, and public impact.
The property benefits from an excellent connectivity within Quitos metropolitan public transport
system:
Direct access to the “La Carolina” station of the Quito Metro, which receives an estimated daily influx
of more than 10,000 passengers.
Proximity to the Trolleybus and Express bus line systems, enabling efficient access from multiple
areas of the city and strengthening the sites regional integration.
The combination of its strategic location, multimodal connectivity, and high-quality urban surroundings positions this site a strategic point for the development of the new National Museum of Ecuador, ensuring the integration of culture, public space, and mobility within the active fabric of the
contemporary city.
10
11
III. PARTICIPATION
REQUIREMENTS - STAGE 1
III. PARTICIPATION REQUIREMENTS - STAGE 1
STAGE 1: CALL FOR CREDENTIALS AND PORTFOLIOS
The National Government of Ecuador, through the Ministry of Education, Sports and Culture, invites
national and international architecture professionals to submit their credentials and portfolios. Based
on this evaluation, the teams that will participate in Stage 2— the Open Call for Architectural design proposals (schematic design) of the new building of the National Museum of Ecuador—will
be selected.
1. Modality of the Open call
National and international Open Call
2. Participants
Applying teams must demonstrate the technical, creative, and professional capacity necessary for the development of the project, as well as previous experience that validates their
suitability to undertake a museum building of this scale and complexity.
The following may participate:
Natural persons or legal entities, national or foreign.
Multidisciplinary teams, made up of professionals from different areas related to architectural, museographic, urban, and engineering design, must designate a Project Director (the
teams representative).
The team must demonstrate experience, technical and interdisciplinary capacities, incorporating specialists in the various areas related to museum design and associated typologies.
Professionals whose degrees and professional registrations are duly validated by SENESCYT (for Ecuadorians) or by the competent authority in their country of origin (for foreign
participants) will be eligible.
13
The basic team will be made up of, at least:
Project Director (Architect)
Sénior Architect 1
Sénior Architect 2
Urban Landscape Specialist
Museum Specialist
Structural Engineering and Civil Projects Specialist
Specialist in Eco-efficiency, Sustainability and Energy Resources
The following are not eligible to participate:
Individuals who have a second-degree consanguinity or affinity relationship, and/or a
corporate or partnership relationship (shareholder, partner, etc.), with any member of the
Stage 2 Jury.
Individuals who maintain an employment relationship with the Ministry of Education,
Sports and Culture.
Individuals who are involved in legal disputes with the Ministry of Education, Sports and
Culture.
Individuals who are currently disqualified, suspended, or otherwise restricted by the
College of Architects of Ecuador (applicable only to Ecuadorian architecture professionals).
Any natural or legal person who has been involved, in any capacity, in prior studies, advisory services, consultancies, preliminary designs, or preparatory work related to the project shall be disqualified from submitting subsequent claims regarding the designs or any
results arising from this process. This provision ensures transparency, prevents conflicts of
interest, and protects the technical integrity of the competition.
Individuals who have been involved in the preparation of the technical bases of this
competition.
The same professional may not be part of more than one team.
3. Enabling documents
The qualifying documentation comprises the formal and verifiable requirements that applicant
teams must submit to demonstrate their interest, technical capacity, and professional experience— including the evaluation of their portfolio—prior to their classification for the next
stage of the Open Call.
3.1. Letter of interest and commitment
A letter of interest and commitment signed by the Project Director, who will act as the official representative of the team, expressing the teams motivation to participate, its willingness to undertake the project, and its agreement to the terms of the competition. The letter
must be submitted in accordance with the format provided in Annex 1.
3.2. Team Members
The base team must be composed of at least the positions described below. The teams portfolio will be supported by the experience of each of its members, who must comply with the
following requirements:
14
Member
Degree
Verifiable
experience
Specific experience with the form of
presentation described (Attached in PDF)
Project
Director
Architect
More than ten (10)
years of verifiable
professional
experience
Experience in the design of public-use building
in general, and cultural buildings or museums in particular, whether as the author or as a
member of the responsible firm, will be valued.
Sénior
Architect(s) 1
Architect
More than ten (10)
years of verifiable
professional
experience
Experience in the design of projects for public-use building in general, and for cultural
buildings in particular—whether as the lead
designer or as a member of the responsible
firm—will be valued.
Sénior
Architect(s) 2
Architect
More than ten (10)
years of verifiable
professional
experience
Experience in the design of projects for
public-use building in general, and cultural
buildings in particular, for which they are the
author or in which they have participated as a
member of the responsible firm, will be valued.
Author
specializing
in Urban
Landscape
Architect
More than ten (10)
years of verifiable
professional
experience
Experience in public-use building projects in
general, and in cultural buildings in particular,
in which they have been responsible for the
landscape design and outdoor spaces or have
participated as a member of the authoring firm,
will be valued.
Architect / More than ten (10)
Designer / years of verifiable
Set Designer professional
experience
Experience in designing exhibitions on
different topics, and especially in exhibitions
on archaeology, art, or any cultural or science
exhibitions, will be valued.
Museum
designer
Structural
and civil
works
engineer
Civil
Engineer
More than ten (10)
years of verifiable
professional
experience
Experience in public-use building projects in
general, and in cultural buildings in particular,
in which they have been responsible for the
structural design will be valued.
Specialist in
Architect or More than five (5)
ecosustainability years of verifiable
efficiency,
specialist.
professional
sustainability
experience
and energy
resources
Experience in public-use building projects in
general, and in cultural buildings in particular,
where they have been responsible for integrating
environmental and energy-efficiency criteria
will be valued.
15
3.2.1. Team member verification documents:
A list of all team members, specifying their roles in accordance with the requirements and
using the format provided in Annex 2. The list must indicate whether each team member
is part of the architecture firm or is participating under a specific contractual agreement.
A Curriculum Vitae for each team member, including a 150-word summary highlighting
their relevant professional background, as well as their participation in projects, awards,
and recognitions related to public-use buildings (not residential or industrial). Each CV
must be submitted as a single DIN A4 PDF file.
3.2.2. Team experience
Teams interested in participating must demonstrate their technical, creative and delivery capacity, for which they must submit:
A)
A list of at least three (3) built public-use building projects, specifying their typology and
surface areas, demonstrating programs and technical solutions of high complexity. The
list must follow the format provided in Annex 2.
B)
A list of at least one (1) cultural building project constructed and/or under construction—
such as museums, cultural centers, public libraries, auditoriums, concert halls, or related
typologies—specifying its typology and surface areas, and demonstrating programs and
technical resolutions of high complexity. The list must follow the format established in
Annex 2.
C)
A list of awards and recognitions received by the team members, submitted in accordance
with the format provided in Annex 2.
3.2.3. Portfolio of projects of the team to be evaluated:
Applicant teams must submit a portfolio of projects authored by the participating architecture
firm(s) or professionals that are part of the team, demonstrating compliance with the general and
specific experience requirements below.
General Experience:
A. Applicants must submit a selection of at least three (3) built public-use building projects, specifying their typology and surface areas, demonstrating programs and technical solutions of high
complexity. For each project, an A3 sheet containing the following información must be included:
• Project: Name and description of the project (max. 150 words)
• Year: Year of construction
• Location: Country and city
• Promoter / Client: Name of the client or commissioning entity
• Gross Floor Area: Expressed in square meters
• Useful Floor Area; Expressed in square meters
16
Authors: List of authors and co-authors
Graphic Documentation (Format: 1 DIN A3 per project)
Specific experience:
B. Applicants must submit at least one (1) cultural building project, built and/or under
construction—such as museums, cultural centers, public libraries, auditoriums, concert
halls, or related typologies—specifying its typology and surface areas, and demonstrating programmatic and technical resolutions of high complexity.
Project: Name and description of the project (max. 150 words)
Year: Year of construction
Location: Country and city
Promoter / Client: Name of the client or commissioning entity
Gross Floor Area: Expressed in square meters
Useful Floor Area; Expressed in square meters
Authors: List of authors and co-authors
Graphic Documentation (Format: 1 DIN A3 per project)
The projects presented in the portfolio must include plans and photographs accompanied by a
descriptive text. When possible, a web link providing additional information about the project may
be included.
The certificates of authorship or co-authorship of the projects presented must be attached as an
annex.
C. Awards and Recognition:
Submit the teams awards and recognitions, including the name of the award, year,
country, and a description of up to 50 words each, following the format provided in Annex 2.
17
View of Quito, 1860. Rafael Salas. Oil on cardboard. National Collection of Ecuador.
IV. SCHEDULE AND
DELIVERY METHOD
- STAGE 1
IV. SCHEDULE AND DELIVERY METHOD - STAGE 1
1. General Schedule for Stage 1
The following calendar establishes the official dates for Stage 1 Call for Credentials and
Portfolios which runs from the launch of the call to the selection of the teams that will advance to Stage 2. Applicants are encouraged to carefully review each milestone to ensure compliance with the established deadlines
STAGE 1 - Call for Credentials and Portfolios
N.
MILESTONE
DATE
1
Official launch of the Open call
December 2, 2025
2
Questions from participants
January 13, 2026
Inquiries will be received from the launch of the contest until
January 13, 2026, at 23:59 (UTC5).
3
Responses to participant inquiries
January 20, 2026
Responses can be submitted until January 20, 2026 at 23:59
(UTC5). The answers to the queries will be published on the Open
Calls website.
4
Portfolio and credential delivery
March 03, 2026
Applicants may submit their documentation until February 17, 2026
at 23:59 PM (UTC5).
5
Publication of selected teams and formal invitation to finalists March 03, 2026
Those selected will be contacted by the Portfolio Selection
Committee and the selected teams will be published on the open
calls website until the 03 of March 2026.
6
Publication of selected teams and formal invitation to finalists Until the 03th of March,
Those selected will be contacted by the Portfolio Selection Com- 2026
mittee and the selected teams will be published on the open calls
website until the 03 th March 2026.
STAGE 2 Schematic Design Proposals Architectural
N.
MILESTONE
DATE
1
Publication of technical bases Stage 2
Coming soon
20
2. Questions & Answers
Participating
teams
may
submit
questions
to
the
following
email
address:
preguntas@museonacional.gob.ec, between December 2, 2025 and January 13, 2026, until
23:59 (UTC5), in accordance with the established schedule.
Responses to the inquiries will be provided by the organizing body of the competition and will be sent through the email designated by Tuesday, January 20, 2026, at 23:59
(UTC5), in accordance with the established calendar.
For additional information, applicants are encouraged to check the official competition website:
https://construccion.museonacional.gob.ec
3. Form of Delivery of the Requirements Stage 1
The Project Director, acting as the official representative of the applicant team, must submit the
enabling documentation detailed in Section III, Requirements to Participate, numeral 3 (Enabling
Documentation) of these technical bases. All documentation must be submitted in digital format and
must include the corresponding signatures of responsibility.
The email must be sent with the subject line indicated in the template (Annex 3) and must include
the complete identification of the applicant team.
All applications and enabling documentation must be sent to the following email address:
convocatoria@museonacional.gob.ec
Files must not be attached directly to the email. All supporting documentation must be uploaded to a
cloud storage platform (Google Drive, OneDrive, Dropbox, etc.) in strict compliance with the following
requirements:
Consolidation: All documents must be contained in a single compressed file in .ZIP format.
Data integrity: An MD5 hash code corresponding to the .ZIP file must be provided to verify that
the information has not been altered.
Access: The download link must be included in the body of the email and configured with public or unrestricted read permissions to ensure immediate access.
The deadline for submission is February 17, 2026 at 23:59 (UTC5).
Once submitted, the documents may not be edited.
No submissions will be accepted after the deadline.
The organizer of the Open Call will confirm receipt of the application in response
to the email sent by the representative of each team.
4. Language
Since it is a national and international competition, the documentation may be submitted in
Spanish or English.
21
Paul Bar, Puente de la Alameda, 1915. Oil on canvas. National Collection.
22
V. SELECTION PROCESS STAGE 1
V. SELECTION PROCESS - STAGE 1
The selection criteria established for Stage 1 are intended to identify teams that demonstrate the
professional, technical, and creative capacity required to advance to Stage 2 of the open call. The evaluation
will be based on the strength of the credentials, the quality and relevance of the portfolio, and the teams
proven experience in related projects, ensuring that those selected possess the necessary profile to
develop the schematic architectural design for the new building of the National Museum of Ecuador.
1. The Portfolio Selection Committee
The Portfolio Selection Committee is the body responsible for analyzing and evaluating
the documentation submitted by applicant teams during Stage 1, ensuring a transparent
and impartial process aligned with the technical criteria established in these bases.
Its composition includes institutional representatives and specialists in architecture and
museum design, who will ensure that the selected teams possess the professional solvency
required to advance to Stage 2.
The voting members will deliberate and make selection decisions in accordance with the established evaluation criteria. The institutional delegates must be architects or specialists in museography in order to provide technical judgment during the evaluation.
The non-voting member will participate as an overseer of the process, contributing criteria and substantive knowledge regarding the needs of the project and of the National Museum of Ecuador. Their
role is to accompany the review, provide observations, and ensure that the process is conducted with
transparency and institutional relevance, even though they are not part of the final decision-making.
Stage 1 Portfolio Selection Committee of Stage 1 will be made up of:
Voting members:
Institutional technical delegates:
• Vice President of the Republic or their delegate
• Minister of Education, Sports and Culture or their delegate
• Ministry of Infrastructure and Transport or their delegate
Technical delegates:
President of the College of Architects of Ecuador (CAE-P) or their delegate
International specialist in museum design
No-voting members /Overseers:
Executive Director of the National Museum of Ecuador
The Stage 2 Jury will be announced by December 31, 2025.
2. Evaluation Criteria
Before beginning the technical evaluation, it will be verified that the application has been submitted
in full and in accordance with the provisions of the bases, including all enabling documentation,
24
signatures of responsibility, and required annexes. Only complete applications
proceed to the next phase of review.
will
In order to recognize the importance of situated knowledge and cultural relevance in a project of the scale and significance of the National Museum of Ecuador, all evaluation criteria will include an additional weighting for teams with local experience. This weighting seeks to ensure that the proposals reflect a deep understanding of the countrys
identity, spatial context, and cultural conditions, thereby strengthening the role of Ecuadorian
architecture in the development of public facilities and spaces of high significance for society.
2.1. Evaluation of the Proposed Task Force
Compliance with all minimum requirements for the technical team will be verified, including the
mandatory composition of the team, the professional qualifications of its members, and their
respective credentials. This stage is enabling in nature: it does not assign scores and operates strictly as an exclusion criterion. Only teams that meet all requirements will
advance to the subsequent evaluation stages.
A single professional may assume two roles within the core
they possess the necessary experience for each role.
team,
as
long
as
2.1 Evaluation of the proposed technical team
Member
Criterion
Project Director
Has 10 or more years of experience in the design of projects for
public-use buildings in general, cultural buildings or museums in
particular, either as the author or as a member of the responsible
firm.
Sénior Architects 1
More than ten (10) years of verifiable profesional experience
Sénior Architects 2
More than ten (10) years of verifiable profesional experience
Urban Landscape Specialist
More than ten (10) years of verifiable profesional experience
Museum Designer
More than ten (10) years of verifiable profesional experience
Structural and civil works
engineering
More than ten (10) years of verifiable profesional experience
Specialist in eco-efficiency,
sustainability and energy
resources
More than five (5) years of verifiable profesional experience
25
2.3. Evaluation of Team Experience - Portfolio
2.3.1. Evaluation of experience based on quantity of projects
This evaluation reviews the experience demonstrated through built projects or projects currently under construction, organized into two categories: public-use buildings and cultural buildings,
as established in the technical bases. Quantification is carried out solely on the number of projects submitted and the minimum number required per building typology, verifiable through
project sheets, certificates of authorship or co-authorship, and other supporting documents.
2.3.1. Evaluation of Experience by Number of Projects
General Experience Public-Use Buildings
A
Feature
Minimum
Public-use buildings
Must present a minimum of 3 projects.
Can present more than 3 projects
Specific Experience - Cultural Buildings
Feature
B
Minimum
Cultural buildings
Must present a minimum of 1 project.
Can present more than 1 project
2.3.2. Qualitative Evaluation of the Portfolio
The qualitative evaluation is the most significant component of the selection process and involves
an in-depth assessment of the architectural, urban, and technical quality of the projects presented
in the portfolio. It applies only to teams that have previously met all documentary verification requirements and the minimum profile of the proposed technical team.
The evaluation is based on the following four criteria:
Criterion 1. Typological Relevance and Coherence
This criterion assesses whether the submitted works are appropriate to the building type (public,
cultural, or museum-related), whether they correspond to the complexity of the assignment, and
whether they demonstrate experience comparable to the level required for a national museum.
Criterion 1. Typological and Scale Relevance and Coherence
General Experience - Public-use buildings
Project
Outstanding
Adequate
Limited
Insufficient
Public
-use
buildings
Projects that are
totally pertinent and
coherent with their
scale and typology.
Projects with relevance
and coherence appropriate to their scale and
typology
Projects with low
coherence and out of
typology.
Without relevance
or coherence in
scale or typology.
Specific Experience - Cultural Buildings
Project
Outstanding
Adequate
Limited
Insufficient
Cultural
buildings
Projects that are
totally pertinent and
coherent with their
scale and typology.
Projects with relevance
and coherence appropriate to their scale and
typology.
Projects with low
coherence and out of
typology.
Without relevance
or coherence in
scale or typology.
26
Criterion 2. Conceptual, spatial and formal coherence
This criterion assesses the clarity of the architectural concept; the quality of interior and exterior spatial composition; the alignment between form, function, and program; and the expressive rigor of the architectural language demonstrated across the projects.
Criterion 2. Conceptual, spatial and formal coherence
General Experience - Public-use buildings
Project
Outstanding
Adequate
Limited
Insufficient
Public
-use
buildings
Architecture with
excellent coherence
and expressiveness
Architecture with
adequate coherence and
expressiveness.
Architecture with
weak coherence,
spatial , and unclear
formal resolution.
Architecture
lacking conceptual, spatial and
formal coherence.
Specific Experience - Cultural Buildings
Project
Outstanding
Adequate
Limited
Insufficient
Cultural
buildings
Architecture with
excellent coherence
and expressiveness
Architecture with
adequate coherence and
expressiveness.
Architecture with
weak coherence,
spatial , and unclear
formal resolution.
Architecture
lacking conceptual, spatial and
formal coherence.
Criterion 3. Technical, constructive and material soundness:
This criterion evaluates the quality of the architectural solutions, the appropriate use of
materials and technical systems employed, and the level of definition achieved in the
projects. It assesses the teams ability to develop buildings with solid technical resolution.
Criterion 3. Technical, constructive and material solidity
General Experience - Public-use buildings
Project
Outstanding
Adequate
Limited
Insufficient
Public
-use
buildings
High technical
and material
resolution.
Meets overall
technical standards
Evident constructive
weaknesses or
deficiencies.
Poor or insufficient
technical and material
resolution.
Specific Experience - Cultural Buildings
Project
Outstanding
Adequate
Limited
Insufficient
Cultural
buildings
High technical
and material
resolution.
Meets overall
technical standards
Evident constructive
weaknesses or
deficiencies.
Poor or insufficient
technical and material
resolution.
27
Criterion 4. Relationship with the environment: This criterion evaluates the projects integration within its urban and landscape context, the quality of its site placement, its handling of public
space, its dialogue with the surrounding environment, and its sensitivity to contextual conditions.
Criterion 4. Relationship with the environment
General Experience - Public-use buildings
Project
Outstanding
Adequate
Limited
Insufficient
Public
-use
buildings
Impeccable site integration,
appropriate scale, and a clear
contribution to the urban
environment.
Correct relationship with
the environment
Weak or poorly
integrated site
placement.
Does not
respond to the
urban context.
Specific Experience - Cultural Buildings
Project
Outstanding
Adequate
Limited
Insufficient
Cultural
buildings
Impeccable site integration,
appropriate scale, and a clear
contribution to the urban
environment.
Correct relationship with
the
environment
Weak or poorly
integrated site
placement.
Does not
respond to the
urban context.
2.3.3. Evaluation of awards and recognitions
Relevant awards, distinctions, and honorable mentions associated with the teams
architectural works—or those of its members—granted by competent and discipline-related institutions will be evaluated.
First prizes will receive a higher weighting, while second and third places or honorable mentions
will receive a lower weighting.
Only a limited number of awards will be considered for evaluation.
3. Selection of teams for Stage 2.
Stage 1 does not include monetary awards, as its purpose is to identify teams with the
vision, experience, and technical soundness required to advance to the next stage.
In Stage 2, the selected teams will present their schematic architectural design proposals. Only one team will be selected, which will receive a financial allocation of
USD 450,000 (Four hundred fifty thousand american dollars). This allocation includes the complete
delivery of the schematic design in accordance with the requirements established in Stage 2 bases.
If a selected team is composed of more than one firm, the firms must establish a formal consortium and
officially designate a Project Director, who will assume the official representation of the team.
The second-place finalist and any honorary mentions, if granted, will not receive monetary
compensation; however, their proposals will be included in the public exhibition of design alternatives, providing visibility and recognition within the process.
28
Araceli Gilbert, Horizontal Construction, 1973. Acrylic on wood. National Collection.
29
Effigy Bottle
35003350 BCE
Mayo-Chinchipe culture, Santa AnaLa Florida, Zamora
National Collection of Ecuador
30
VI. ANNEXES
31
ANNEX 1. Letter of interest
Call to submit credentials and portfolios for the selection of teams for participation in
the Open Call for Architectural schematic design proposals for the New Building of the
National Museum of Ecuador.
I, Arch. ________________________, with identification/passport ________________________,
representative of the participating team for the selection of credentials and portfolios for participation in the Open Call for Architectural schematic design proposals for the New Building of the
National Museum of Ecuador, hereby undertake, state my interest in participating in this process
and commit, if selected, to submit the required proposal within the deadlines established and in accordance with the conditions set forth in the Participation Rules and all other project documentation.
Furthermore, I acknowledge that, if selected to participate in Stage 2 of the Open Call for the Design
of the Architectural Preliminary Project for the New Building of the National Museum of Ecuador,
I may have access to confidential or privileged information related to the project. I hereby agree to
maintain the strictest confidentiality regarding such information and to refrain from disclosing it to
third parties. I understand that any unauthorized disclosure may result in the termination of my participation in the process and the application of legal measures in accordance with applicable laws
and regulations.
Place and Date: ________________________
______________________
Signature
[Name of Project Director] [Professional Title] [Phone] [Email] [Name of Team / Studio / Firm
32
ANNEX 2. Summary of the team roster, quantitative
project experience and awards
TABLE 1. TEAM MEMBERS
Full name
Role
Team
Representative
1*
Project Director
X
2*
Sénior Architect 1
3*
Sénior Architect 2
4
Urban Landscape
Specialist
5
Museum
specialist
6
Structural and civil
works engineer
7
Specialist in eco-efficiency and
sustainability
Architecture Firm /
Independent
TABLE 2. TEAM EXPERIENCE
2.1. GENERAL EXPERIENCE (PUBLIC-USE BUILDINGS)
Project
Name
Location
Typology
Gross
Floor
area
(m2)
Usable
Floor area
(m2)
1*
2
3
4
5
6
7
33
Year
Promoter
Authors
Verification
document
(link, certificate, etc.)
DIN A3,
Renderings,
planimetry
TABLE 2. TEAM EXPERIENCE
2.2. SPECIFIC EXPERIENCE (CULTURAL BUILDINGS)
Project
Name
Location
Typology
Gross
Floor
area
(m2)
Usable
Floor area
(m2)
Year
Promoter
Authors
Verification document
(link, certificate, etc.)
1
2
3
4
5
6
7
TABLE 3. TEAM AWARDS AND RECOGNITIONS
First Prize
Name
Institution
Project
Name
Year
Country
Container
Verification
document (link,
certificate, etc.)
1*
2*
3*
4
5
6
7
Second, third prize and mentions
Name
Institution
Project
Name
Year
Country
Container
Verification
document (link,
certificate, etc.)
*Minimum Information
NOTE: Team members' Resumes do not have an established format or template, they
must only meet the requirements stipulated in section III. Requirements to participate.
34
ANNEX 3. Submission Template Documentation
and Application Stage 1
To: convocatoria@museonacional.gob.ec
Subject: Credential and Portfolio Delivery Stage 1
Dear Members of the Organizing Committee,
I hereby submit the enabling documentation, credentials, and portfolio corresponding to Stage 1 of
the Open Call for Architectural schematic design proposals for the New Building of the National Museum of Ecuador.
I act as Project Director and representative of the applicant team [Team Name, if applicable], in compliance with the requirements established in the technical bases, including all documentation duly
signed and submitted in digital format.
The enabling documentation, annexes, and portfolio can be accessed at the following link:
I would like to confirm receipt of these documents.
I remain attentive to any additional communication related to the process.
Cordially,
[Name of Project Director] [Professional Title] [Phone] [Email] [Name of Team / Studio / Firm
35
Patria, 1922, Luis Mideros, Óleo sobre lienzo, Colección Nacional.
36
There is only one National Museum
per country.
This is Ecuadors.
Social Media:
@caepichincha
@museonacionalecuador
@lacoleccionnacional
@culturaypatrimonioec
https://construccion.museonacional.gob.ec